These articles provide an outline of the tasks school admins must carry out to prepare DPR for a new academic year. We highly recommend school admins familiarise themselves with these steps before the end of the summer term to provide enough time to plan.
- It is recommended schools finalise key objectives for the new academic year before the end of July
-
MIS Sync will be disabled on the 1st of July and will need to be re-enabled by your school's admin
- The academic year start date is set to the 15th of August by default. If your school's academic year start date starts earlier than this, please ensure you have updated the start date before re-enabling mis-sync
- We have broken down the required tasks into tasks for August and tasks for September